OR-Notes are a series of introductory notes on topics that fall under the broad heading of the field of operations research (OR). They were originally used by me in an introductory OR course I give at Imperial College. They are now available for use by any students and teachers interested in OR subject to the following conditions.
A full list of the topics available in OR-Notes can be found here.
Information concerning a certain project is given in the table below. Indirect project costs amount to £250 per day. The company will experience a £100 per day penalty for each day the project lasts beyond day 14.
Activity Normal Normal Crash Crash Immediate time cost time cost predecessor (days) (£) (days) (£) activities
A 4 1000 3 1100 - B 6 800 3 2000 - C 3 600 2 800 A,B D 2 1500 1 2000 B E 5 700 3 1200 C,D F 2 1300 1 1400 E G 2 900 1 1200 E H 4 100 2 900 G