Network analysis - activity on node tutorial question
The following table defines the various activities in a small project:
Activity Completion time (weeks)
1 1
2 4
3 2
4 6
5 2
6 5
7 3
8 6
9 1
The immediate precedence relationships are:
Activity Activity
number number
1 must be finished before 3 can start
2 4,5,6
3 5,6
4 7
5 8
6,7 9
- Draw the network diagram.
- Calculate the critical activities, the overall project completion time
and the total float times for each activity.
- How would the overall project completion time be affected if the following
were to happen (where you should take each of the situations below separately,
do not try and estimate the effect if they both happen):
- the completion time for activity 6 increased from 5 weeks to 7 weeks?
- the completion time for activity 8 could be cut from 6 weeks to 4 weeks?
- A colleague is arguing that if the completion time for activity 4 (a
critical activity) could be cut by 3 weeks then the time taken to complete
the entire project could also be cut by 3 weeks. Would you agree or not?
If not what effect would cutting the completion time for activity 4 by
3 weeks have?
- Comment on the progress of the project if (ignoring the changes in
completion times given above), at the end of 8 weeks, the status of the
activities is as follows:
- Finished - 1,2,3
- In progress - 4 (1 week to completion)
- In progress - 5 (1 week to completion)
- In progress - 6 (4 weeks to completion)