OR-Notes

J E Beasley

OR-Notes are a series of introductory notes on topics that fall under the broad heading of the field of operations research (OR). They were originally used by me in an introductory OR course I give at Imperial College. They are now available for use by any students and teachers interested in OR subject to the following conditions.

A full list of the topics available in OR-Notes can be found here.


UG examination 1998

Answer FOUR questions.
All questions carry equal marks.
If more than four questions are answered only the first four answered will be marked.
Marks will be deducted in this examination if there is insufficient written explanation.

Question 1

The table below defines the activities that have been provisionally planned within a small project.

     Activity                 Completion               Immediate
                              time                     predecessor
                             (weeks)                   activities
      A                        3                           B
      B                        5                           C
      C                        4                           -
      D                        8                           B,A
      E                        3                           A,C
      F                        2                           E
  • Draw the network diagram.
  • Calculate the minimum overall project completion time and identify which activities are critical.
  • What is the slack (float) time associated with each of the non-critical activities.
  • Comment upon the project if, after 6 weeks, the status of the activities is as follows:
  • If the situation is as after 6 weeks above, but now the completion time for activity D is uncertain (optimistic time 4 weeks, most likely time 6 weeks, pessimistic time 10 weeks), comment upon the project.

    Question 2

    A company is comparing the performance of a number of its branches using data envelopment analysis. The data for these branches involves two output measures and one input measure. The output measures are profit per square metre and average customer feedback (from zero to ten, ten being excellent). The input measure is staff cost. This data is as shown below

          Branch      Profit               Customer      Staff
                      per sq metre         feedback      cost (£'000)
          1           6.3                  5.6           230
          2           4.5                  3.3           240
          3           3.7                  4.5           300
          4           6.7                  7.8           550

    Question 3

    The data below shows the earliest and latest landing times for a set of planes waiting to land at London Heathrow. All times are measured in seconds from a common origin. Heathrow has two runways which are operated in segregated-mode, that is one runway is dedicated to landings only and the other runway is dedicated to take-offs only.

          Plane        Earliest time        Latest time          Type
          1            10                   650                  1
          2            30                   750                  1
          3            50                   850                  2
          4            70                   930                  2

    For example the earliest plane number 1 can land is time 10, the latest it must land is time 650 and it is of type 1.

    The plane type relates to the required separation time needed between the landing of two successive planes. These separation times are shown in seconds below.

                                   First plane type
                                   1        2
         Second plane type 1       180      250
                           2       130      90

    For example once a plane of type 2 has landed at least 250 seconds must elapse before a plane of type 1 can land.

    The objective is to land all planes as quickly as possible (i.e. to minimise the landing time of the last plane to land).

    Develop TWO integer programming formulations of the above problem:

    Question 4

    In analysing switching by commuters between car, bus and tube as the mode of transport for their daily journeys to work in London a Government task force has obtained the following data:

                                           Next daily journey by:
                                           Car     Bus     Tube
         Last daily journey by:   Car      0.95    0.01    0.04
                                  Bus      0.15    0.50    0.35
                                  Tube     0.10    0.10    0.80

    For example if the last daily journey was by car then the probability that the next daily journey is by bus is 0.01. If initially 25% of commuters travel by car, 15% by bus and 60% by tube what proportion will travel by each mode of transport after another two daily journeys?

    What is your forecast for the long-run proportion of commuters travelling by car, bus and tube?

    Question 5

    A company requires a part at the rate of 500 units per month. The part costs £20 per unit when purchased from an outside supplier. The cost of making an order is estimated to be £180 and the company uses an interest rate of 10% per annum.

    Question 6

    Useful Products, a company manufacturing a number of different oral hygiene products, have developed a new mouthwash (codenamed ABC). Useful have to decide whether to introduce ABC to the market nationally or not. After careful consideration of all options the management of Useful have narrowed their options to three:

    If ABC is introduced on a trial basis locally the trial would cost £150,000 and based on similar past trials there is a 65% chance that ABC would be successful locally. Analysis of past history has revealed that a product successful on a local basis has a 80% chance of being successful on a national basis. However even if ABC is unsuccessful locally there is still a 45% chance that it would be successful nationally.

    If ABC is introduced nationally without local trials there is a 55% chance that it would be a success. If ABC is successful nationally it will give a net return of £700,000, but a net loss of £250,000 if it is a failure nationally.

    Show the above scenario as a decision tree and then recommend what action Useful should take to maximise its net return.