OR-Notes are a series of introductory notes on topics that fall under the broad heading of the field of operations research (OR). They were originally used by me in an introductory OR course I give at Imperial College. They are now available for use by any students and teachers interested in OR subject to the following conditions.
A full list of the topics available in OR-Notes can be found here.
In a project there are 9 activities as below (all times in months):
Activity Optimistic Most likely Pessimistic Immediate predecessor
time time time activities
A 4 6 8 -
B 1 2 3 -
C 4 4 4 A
D 4 5 6 A
E 7 10 16 B
F 8 9 10 B
G 2 2 2 C
H 2 3 7 D,E,F
I 1 3 11 F
Activity Optimistic Most likely Pessimistic Immediate predecessor
time time time activities
A 8 10 12 -
B 5 8 17 -
C 9 10 11 -
D 1 2 3 B
E 8 10 12 A,C
F 5 6 7 D,E
G 1 3 5 D,E
H 2 5 8 F,G
I 2 4 6 G
J 4 5 8 H
K 2 2 2 H
Activity Normal Normal Crash Crash Immediate
time cost time cost predecessor
(days) (£) (days) (£) activities
A 4 1000 3 1100 - B 6 800 3 2000 - C 3 600 2 800 A,B D 2 1500 1 2000 B E 5 700 3 1200 C,D F 2 1300 1 1400 E G 2 900 1 1200 E H 4 100 2 900 G