OR-Notes are a series of introductory notes on topics that fall under the broad heading of the field of operations research (OR). They were originally used by me in an introductory OR course I give at Imperial College. They are now available for use by any students and teachers interested in OR subject to the following conditions.
A full list of the topics available in OR-Notes can be found here.
The network diagram is shown below.
The network diagram is shown below.
The network diagram is shown below.
We tabulate below the costs for all durations below 20 days
duration project penalty indirect total cost cost cost cost 20 6900 600 5000 12,500 19 7100 500 4750 12,350 18 7350 400 4500 12,250 17 7600 300 4250 12,150 16 7900 200 4000 12,100 15 8300 100 3750 12,150 14 8700 - 3500 12,200 13 9100 - 3250 12,350
Best solution is to crash to 16 days duration by crashing C 1 day, E 2 days, and G 1 day