OR-Notes are a series of introductory notes on topics that fall under the broad heading of the field of operations research (OR). They were originally used by me in an introductory OR course I give at Imperial College. They are now available for use by any students and teachers interested in OR subject to the following conditions.

A full list of the topics available in OR-Notes can be found here.


Network analysis tutorial solution

The network diagram is shown below.


The network diagram is shown below.


The network diagram is shown below.

We tabulate below the costs for all durations below 20 days

        duration         project         penalty         indirect         total
                         cost            cost            cost             cost
        20               6900            600             5000             12,500
        19               7100            500             4750             12,350
        18               7350            400             4500             12,250
        17               7600            300             4250             12,150
        16               7900            200             4000             12,100
        15               8300            100             3750             12,150
        14               8700            -               3500             12,200
        13               9100            -               3250             12,350

Best solution is to crash to 16 days duration by crashing C 1 day, E 2 days, and G 1 day